Project Description
6 White Ave
Ecuabuilder ltd. was communicated to by the owner on May 2012. The existing structure was 1 story wood structure. Ecuabuilder ltd. was contracted to demolish existing structure and complete 2 story new construction.
Scope:
- Design new floor plan for first floor and second floor.
- Create working drawings
- Apply and receive building permits
- Demolish of existing walls on first floor and existing roof
- Install new stairs
- New construction (wood framing) of 1st and 2nd floor.
- New plumbing, new hvac, new electrical all inspected and pass by the city of Toronto.
- Interior work (insulation, gypsum board and plaster).
- Interior finishes (floors, walls, ceiling, kitchen cabinets, fireplace and lights).
Project Details
DATE
May 2012
CLIENT
6 White Ave.
PROJECT TYPE
Residential